Thought I would get in the following analysis before the naysayers do:-
Don't be fooled, RD is just an asset stripper, this is just part of a scheme to own an asset created from other peoples money he can strip out later on.
Dippenhall - please explain. All I see is another positive step for CAFC`s youth set up upgrading status to protect player investment with the owner seeking as much outside investment as possible.
Applications, once submitted, have to be validated by the council. This can take a while with larger applications because the planners will often ask for more information or they might just have a heavy workload. Only once the council is satisfied there is enough information to start the consultation will it be registered and details published. So I wouldn't say the fact it's not in the public domain already means anything.
Charlton will now submit a new planning application to the Royal Borough of Greenwich over the next two weeks, while maintaining dialogue with planning and highways officers.
The club will also continue to seek feedback from residents.
Once submitted, it is anticipated that it will take three-to-four months for the club to receive a decision on its application.
Further details of developments relating to the club's new training ground facility will continue to be published on www.cafc.co.uk over the coming weeks and months.
This development will be a screaming success at every level, providing, as looks likely, it goes ahead. I don't have a clue how it will be paid for, but then again the finances of the club are so convoluted it is very hard to understand all that stuff. Either way, as long as the club don't go bust because of the cost, we will have this facility on our patch which is excellent.
Interesting that the club have gone for the bare minimum size for the indoor pitch rather than the recommended size for Cat One status. I'd guess that was a compromise to try to keep the footprint of the building down to as small a size as possible? I hope they know what they are doing but it seems they are placing a lot of trust on whoever do the Cat One clearance not to use that as an excuse to turn us down.
Comments
Appoint project team 10/11/14
Feasibility studies and concept design 10/11/14 to 19/12/14
Design development for planning 5/1/15 to 30/1/15
Planning submission 30/1/15
Detailed Design Development 30/1/15 to 11/06/15
Planning approval 1/5/15
Procurement and appoint contractor 15/6/15 to 11/9/15
Lead in 14/9/15 to 9/10/15
Construction (14 Months) 21/10/15 to 2/12/16
Start on site 12/10/15
Integrated training Centre and Community Facility 12/10/15 to 15/7/16
Appoint project team 10/11/14
Feasibility studies and concept design 10/11/14 to 19/12/14
Design development for planning 5/1/15 to 30/1/15
Planning submission 30/1/15
Detailed Design Development 30/1/15 to 11/06/15
Planning approval 1/5/15
Procurement and appoint contractor 15/6/15 to 11/9/15
Lead in 14/9/15 to 9/10/15
Construction (14 Months) 21/10/15 to 2/12/16
Handover of site 12/10/15
Does anyone know or can find out if a planning submission was made?
From my limited experience these plans rarely stay on schedule so won't be a surprise or a cause of panic if not but would be interesting to know.
http://publicaccess.royalgreenwich.gov.uk:81/online-applications/simpleSearchResults.do?action=firstPage
Sooner they get this done the better, and alleviate the traffic in Sparrows Lane - (from a personal perspective)
At public consultation stage
The club will also continue to seek feedback from residents.
Once submitted, it is anticipated that it will take three-to-four months for the club to receive a decision on its application.
Further details of developments relating to the club's new training ground facility will continue to be published on www.cafc.co.uk over the coming weeks and months.
Read more at http://www.cafc.co.uk/news/article/residents-take-a-look-at-training-ground-plans-2346967.aspx#yQYzCeQyzElzJKPk.99
Would fit in with ground breaking in October
http://www.cafc.co.uk/news/article/residents-take-a-look-at-training-ground-plans-2346967.aspx